Torrens to Darlington Project

Share Torrens to Darlington Project on Facebook Share Torrens to Darlington Project on Twitter Share Torrens to Darlington Project on Linkedin Email Torrens to Darlington Project link

The Department for Infrastructure and Transport will commence demolition works on 11 sites (16 individual properties) in Clovelly Park from Monday 29th August for approximately 2 months, as part of the Torrens to Darlington (T2D) Project. The properties are being demolished to make way for the Southern Laydown Area – the first major construction works for the T2D Project.


Attached to the 'Documents' section of this project are relevant letters to Clovelly Park residents for reference.


Below are the proposed timeframes for demolition (subject to change).

Site address

Property

Demolition starts

Demolition ends

63 & 65 York Avenue, Clovelly Park

Residential

29 August

19 September

1258-1260 South Road, Clovelly Park

Commercial

31 August

30 September

1246-1250 South Road, Clovelly Park

Commercial

30 August

19 September

49 York Avenue, Clovelly Park

Residential

29 August

9 September

1244 South Road, Clovelly Park

Commercial

30 August

30 September

43 & 45 York Avenue, Clovelly Park

Residential

5 September

11 October

1232 South Road, Clovelly Park

Commercial

12 September

26 October

39 York Avenue, Clovelly Park

Residential

31 August

22 September

1226 South Road, Clovelly Park

Commercial

2 September

12 October

2 Celtic Avenue, Clovelly Park

Residential

6 September

6 October

29 & 31 York Avenue, Clovelly Park

Residential

15 September

4 November

The Department for Infrastructure and Transport will commence demolition works on 11 sites (16 individual properties) in Clovelly Park from Monday 29th August for approximately 2 months, as part of the Torrens to Darlington (T2D) Project. The properties are being demolished to make way for the Southern Laydown Area – the first major construction works for the T2D Project.


Attached to the 'Documents' section of this project are relevant letters to Clovelly Park residents for reference.


Below are the proposed timeframes for demolition (subject to change).

Site address

Property

Demolition starts

Demolition ends

63 & 65 York Avenue, Clovelly Park

Residential

29 August

19 September

1258-1260 South Road, Clovelly Park

Commercial

31 August

30 September

1246-1250 South Road, Clovelly Park

Commercial

30 August

19 September

49 York Avenue, Clovelly Park

Residential

29 August

9 September

1244 South Road, Clovelly Park

Commercial

30 August

30 September

43 & 45 York Avenue, Clovelly Park

Residential

5 September

11 October

1232 South Road, Clovelly Park

Commercial

12 September

26 October

39 York Avenue, Clovelly Park

Residential

31 August

22 September

1226 South Road, Clovelly Park

Commercial

2 September

12 October

2 Celtic Avenue, Clovelly Park

Residential

6 September

6 October

29 & 31 York Avenue, Clovelly Park

Residential

15 September

4 November

Page published: 26 Aug 2022, 01:55 PM