29 August → 19 September 2022

Clovelly Park Demolition Timeframes Guide

Below are the proposed timeframes for demolition (subject to change).

 

Site address

Property

Demolition starts

Demolition ends

63 & 65 York Avenue, Clovelly Park

Residential

29 August

19 September

1258-1260 South Road, Clovelly Park

Commercial

31 August

30 September

1246-1250 South Road, Clovelly Park

Commercial

30 August

19 September

49 York Avenue, Clovelly Park

Residential

29 August

9 September

1244 South Road, Clovelly Park

Commercial

30 August

30 September

43 & 45 York Avenue, Clovelly Park

Residential

5 September

11 October

1232 South Road, Clovelly Park

Commercial

12 September

26 October

39 York Avenue, Clovelly Park

Residential

31 August

22 September

1226 South Road, Clovelly Park

Commercial

2 September

12 October

2 Celtic Avenue, Clovelly Park

Residential

6 September

6 October

29 & 31 York Avenue, Clovelly Park

Residential

15 September

4 November