Aerial image
Underground stormwater retention and detention tanks
Underground electrical infrastructure
September 2026 - project update
Activity on site is currently focussing on underground works including stormwater and electricity infrastructure, ahead of works on the footings and concrete slab. A breakdown of construction activities over the next 5 months is provided below:
| Activity | Expected date |
| Building footing | September 2026 |
| Building Slab | October 2026 |
| Steelworks | November 2026 |
| Roofing | December 2026 |
| Brickwork | January 2027 |
June 2026 project update
After more than six decades of buzzer-beaters, grand finals, packed sidelines and countless hours of training, the wrecking crews took over at one of Adelaide's most iconic basketball venues earlier this month. For more than 60 years, The Shed was the home of basketball in Adelaide's south. Now, the ageing facility is being knocked over to make way for a new chapter.


We will continue to provide updates via Making Marion, and if you need to contact the project team, email communityengagement@marion.sa.gov.au or call 8375 6600.
Project Timeline
-
Timeline item 1 - complete
Development Application process
September - April 2026
-
Timeline item 2 - complete
Selection of preferred contractor
March - April 2026
-
Timeline item 3 - complete
Demolition works (mid-June to mid-July)
Removal of tennis courts, clubhouse and old stadium.
-
Timeline item 4 - complete
Site Shaping
Mid July - Mid August
-
Timeline item 5 - active
Building footings and slab
September - October 2026
-
Timeline item 6 - incomplete
Building steelworks
November 2026
-
Timeline item 7 - incomplete
Roofing
December 2026
-
Timeline item 8 - incomplete
Brickwork
January 2027