Progress photos
September 2026 - project update

Activity on site is currently focussing on underground works including stormwater and electricity infrastructure, ahead of works on the footings and concrete slab. A breakdown of construction activities over the next 5 months is provided below:

ActivityExpected date
Building footingSeptember 2026
Building SlabOctober 2026
SteelworksNovember 2026
RoofingDecember 2026
BrickworkJanuary 2027
June 2026 project update

After more than six decades of buzzer-beaters, grand finals, packed sidelines and countless hours of training, the wrecking crews took over at one of Adelaide's most iconic basketball venues earlier this month. For more than 60 years, The Shed was the home of basketball in Adelaide's south. Now, the ageing facility is being knocked over to make way for a new chapter.


We will continue to provide updates via Making Marion, and if you need to contact the project team, email communityengagement@marion.sa.gov.au or call 8375 6600.


Project Timeline

  • Timeline item 1 - complete

    Development Application process

    September - April 2026

  • Timeline item 2 - complete

    Selection of preferred contractor

    March - April 2026

  • Timeline item 3 - complete

    Demolition works (mid-June to mid-July)

    Removal of tennis courts, clubhouse and old stadium.

  • Timeline item 4 - complete

    Site Shaping

    Mid July - Mid August

  • Timeline item 5 - active

    Building footings and slab

    September - October 2026

  • Timeline item 6 - incomplete

    Building steelworks

    November 2026

  • Timeline item 7 - incomplete

    Roofing

    December 2026

  • Timeline item 8 - incomplete

    Brickwork

    January 2027