Background
The City of Marion is planning an upgrade to Teesdale Crescent Reserve, Plympton Park, in partnership with funding from the South Australian Government. Three upgrade options have been developed for community feedback.
The proposed options include:
- Option A - Irrigation, native planting, shelter and drink fountain (with dog bowl)
- Option B - Irrigation, native planting and drink fountain (with dog bowl)
- Option C - Shelter and native planting (no irrigation)
To support the irrigation system, a water tank and pump are required, as mains water pressure alone is not sufficient. The proposed tank will be a slimline design with screening and could be located with the shelter and / or drink fountain.
As the reserve contains mature trees, any new irrigation infrastructure will be installed outside tree root zones to help protect existing vegetation.
The project may also include local heritage interpretation associated with the Teesdale Smith family of Maryland (1925 – 1965), potentially incorporated into the shelter area.
We invite you to review the three options and share your feedback by completing the short survey below. Your input will help shape the final design for the reserve.
Please also read the Frequently Asked Questions, which may answer some of your queries about the project.
Community drop-in session
Come and speak with Council staff at an onsite drop-in session to learn more about the project and provide your feedback.
Teesdale Crescent Reserve
Tuesday 9 June
4 pm to 6 pm
Consultation closes at 5pm on Friday 19 June 2026.

Have your say
Next steps
-
Timeline item 1 - active
Community consultation opens
27 May 2026
-
Timeline item 2 - incomplete
Onsite drop in session
Tuesday 9 June 4 pm to 6 pm
-
Timeline item 3 - incomplete
Community consultation closes
19 June 2026
-
Timeline item 4 - incomplete
Review of consultation feedback
June 2026
Feedback will be reviewed and, where possible, incorporated into the final upgrade design subject to budget.
-
Timeline item 5 - incomplete
Final Concept Plan
July 2026
The final design will be published on this project page when completed.
-
Timeline item 6 - incomplete
Construction
2026/2027 financial year
Who's listening
Contact Open Space project team on 8375 6600 or email communityengagement@marion.sa.gov.au if you would like a hard copy survey or concept plan or if you require further information about the design.